Boiler body of unit 3 BFG Boiler for power plant of HYUNDAI GREEN POWER, which fabricated through continuous efforts of all participants for this project, has been with complete condition for hydraulic test.
Hydraulic test was implemented as scheduled at 6 of May 18th, 2010. Hydraulic tests for primary and secondary steam generation circuits were implemented as the plan for hydraulic test, and it’s one-off success was confirmed by signatures from each party satisfied with processes of boost pressure, pressure regulation and pressure leakage.
The success of hydraulic test for unit 3 boiler is as a substantial foundation for commissioning and operation of this boiler.